Tuesday, 31 January 2017

8 December 2016 - Site start and frame begins

8 December 2016


Exciting to see the site being cut today, looks fantastic




We  have been told we will have a slab before Christmas


 --------------------------------------------


9 December 2016


Plumbing and drainage has been put in






13 December 2016


Slab preparation in the morning

Progress that day

 
 Boxed in ready for pouring

Front of house from porch



14 December 2016


Waffle pods in place
 
close up of porch footings


15 December 2016


 The slab being poured and smoothed



The finished slab!





Friday, 16 December 2016


Pre-fabricated framing delivered





Monday, 19 December 2016


Up goes the frame in the morning





Drove by in the evening  wow! We didn't expect it to be up already. Last stint of work before the Christmas break.






Cheeky look at the framing - looks great!





Guessing these are just settlement cracks??



No comments:

Post a Comment